G6 · Test readiness
Is the solution complete enough to verify end to end?
- Source
- Stage-Gate®; PRINCE2® stage boundaries; ISO 21502 governance
- Level
- B · established practice
Evidence
Checks
- Every increment meets the Definition of Done
- Deliverables reviewed against the agreed quality criteria
- Code reviewed and the pipeline green
- Configuration deployed to test from the packaged solution; no manual changes in test
How the gate runs
- Predictive
- Phase gate: held once, at the end of the stage.
- Agile (iterative)
- Rolling gate: held per release; item readiness via Definition of Ready, completion via Definition of Done.
- Flow (Kanban)
- Policy gate: explicit exit policies on the board columns, applied to every item.
- Hybrid
- Phase gate per phase, with iterations or flow inside the phase.