G3 · Scope baseline

Do we understand the needs well enough to specify them?

Source
Stage-Gate®; PRINCE2® stage boundaries; ISO 21502 governance
Level
B · established practice

Evidence

Scope statementcriticaldepends on context
Paid discovery reportcriticaldepends on context
Story mapoptionaldepends on context
As-is process modelcriticalwaivabledepends on context
As-is process modelrequiredwaivabledepends on context
Solution context diagramcriticaldepends on context
Solution context diagramrequiredwaivabledepends on context
Fit-gap logrequiredwaivabledepends on context
Source data assessmentrequiredwaivabledepends on context
Glossaryrequiredwaivabledepends on context
Glossaryoptionalany context

Checks

  • Needs confirmed with the people who have them
  • Conflicting needs made visible and owned

How the gate runs

Predictive
Phase gate: held once, at the end of the stage.
Agile (iterative)
Rolling gate: held per release; item readiness via Definition of Ready, completion via Definition of Done.
Flow (Kanban)
Policy gate: explicit exit policies on the board columns, applied to every item.
Hybrid
Phase gate per phase, with iterations or flow inside the phase.