G1 · Commit
Can we commit to scope, price and approach?
- Source
- Stage-Gate®; PRINCE2® stage boundaries; ISO 21502 governance
- Level
- B · established practice
Evidence
Checks
- Delivery approach chosen and recorded
- Contract model fits the uncertainty: fixed price only for clear or complicated scope, or after a paid discovery
- Regulatory obligations listed in the SOW assumptions and priced
- Service levels agreed in the SOW: hours, priorities, response and resolution times
How the gate runs
- Predictive
- Phase gate: held once, at the end of the stage.
- Agile (iterative)
- Rolling gate: held per release; item readiness via Definition of Ready, completion via Definition of Done.
- Flow (Kanban)
- Policy gate: explicit exit policies on the board columns, applied to every item.
- Hybrid
- Phase gate per phase, with iterations or flow inside the phase.